Metal Building Foundations: Why Coordination and Uplift Drive the Design

Writer: Christian Voelkel
Christian Voelkel
Nov 9
4 min read

Alexander Newman, PE, wrote Foundations for Metal Building Systems in the July 2013 issue of STRUCTURE magazine. The article is older, but the mechanics have not gone away. A more recent piece from Vector Structural Engineering, Common Metal Building Foundation Mistakes That Delay Permits or Construction, lists the coordination problems that still stall permits and pours.

Newman’s starting point is that metal building systems are proprietary, lightweight structures. A single-story building can weigh only about 2 to 5 pounds per square foot, so wind often produces net uplift on the foundations. The most common primary frames, gable rigid frames, also put large horizontal reactions at every column. Those two facts together are what make metal building foundations different from many conventional buildings.

Because the buildings are proprietary, different manufacturers can report slightly different column reactions for the same layout and loading. On publicly bid work the manufacturer may not be chosen before the foundations are designed, so the foundation engineer has to estimate reactions and risk a later increase. Newman also notes a common project sequence: the owner buys the building first and treats the foundation as an afterthought. Without a structural engineer setting the frame-base assumptions, a manufacturer may offer fixed-base columns that save a little on the steel and add a lot to the foundations, compared with pin-base columns.

Building codes limit how much dead load can be counted against wind uplift. Newman cites the IBC allowable-stress combination that allows no more than 60 percent of the dead load likely to be in place. For a shallow footing, the ballast is the footing, any pedestal, and the soil on the ledges. The minimum footing size is often set by that ballast requirement, not by downward bearing. His example makes the point plainly: downward load alone suggested about a 3.7-foot square footing, while uplift required an 8-foot square footing about 3 feet 8 inches deep.

The article then compares common systems: tie rods, hairpins with slab ties, moment-resisting foundations, a slab with a haunch, trench footings, mats, and deep foundations. Hairpins are usually the cheapest way to resist horizontal frame thrust, but they depend on the floor slab remaining in place and being detailed carefully. Newman notes that slabs on grade are outside the normal scope of ACI 318 except when they transmit lateral forces, so treating the slab as a structural tie requires more care than a light welded-wire sheet. A later letter to the editor described a hairpin-and-slab job where fiber reinforcement was substituted for welded-wire reinforcement; the slab cracked at the hairpins, the column bases spread, and the roof deflected. Moment-resisting foundations and trench or deep foundations that do not rely on the slab are more versatile when the floor may later be cut, trenched, or omitted.

Vector’s article is more about process than footing theory. The manufacturer’s drawings usually design the steel building, not the site-specific foundation. That foundation still has to account for reactions, anchor bolts, soils, local wind and snow, frost depth, seismic requirements, use, and slab loading. Common delays come from asking for a foundation design without column reactions; using preliminary or outdated building drawings; not explaining how the building will be used; treating the slab as an afterthought; ignoring soils and site conditions; pouring before the package and the foundation plans match; sending the engineer only part of a permit comment letter; and changing the building without updating the foundation design.

Our take

The engineering issue and the scheduling issue are the same issue: the foundation cannot be designed from a brochure. We need the current manufacturer drawings, the anchor-bolt plan, and the column reactions, along with the site address, soils information, and how the building will actually be used.

In Florida, Alabama, and Texas wind country, owners are often surprised that the footings are sized for uplift and overturning rather than for the weight of a light metal building. That is normal. A 2 to 5 psf superstructure does not give the foundation much help, and only part of the dead load can be counted against wind. If someone prices a foundation from downward bearing alone, the number will be too low.

Buying the building first is common, but it should not lock in a fixed-base frame without looking at what that does to the concrete. Pin-base versus fixed-base is one of the earliest decisions that should be coordinated.

Hairpin and slab-tie systems can work when the slab is designed and protected as part of the lateral system. They are a poor fit for a shop or warehouse that may later get trenches, pits, saw-cuts, or a slab replacement. In those cases, a foundation that can stand on its own, a moment-resisting footing, grade beam, trench footing, or deep foundation, chosen for the soils, is the more honest design.

Do not pour until the building revision and the foundation drawings match. Moving a door, changing width, switching manufacturers, or adding a mezzanine can move columns, base plates, bolts, and reactions. Fixing concrete after it is in the ground costs more than waiting for coordinated plans.

 
 
 